Mid February – March: Laying the Foundation

Before the building slab could be poured, the two tracks were put in place and rebar readied for the concrete floor. In early March, 220 cubic yards of concrete were placed in the grade beams, pile caps, and drop pit areas by a massive concrete pump truck whose boom could be seen for blocks away.

Nov 11 – Jan 12 Site Prep & Work Underground

After the building permit was approved work started on the new Enginehouse in November 2011. Site work included preliminary grading and excavation of unwanted materials. Next, a huge crane started driving piles into what turned out to be up to 105′ feet of sawdust before reaching stable rock. One-third of the grout piles were installed successfully …